Route 3 Bridge Replacement

Route 3 Bridge Replacement

MassDOT will be replacing two Route 3 bridges over the Ramp to Quincy Adams/Burgin Parkway. The work will be done over a two weekend timeframe and cranes will be lifting the structures into place, similar to the Fast 14 bridge project that MassDOT did on I-93 over the summer a few years ago.

The plan is to replace the Northbound bridge over the weekend beginning 10PM Friday, 9/22, and roadway access will be back in service before 5AM on Monday 9/25. The Southbound bridge will be replaced over the weekend beginning 10PM Friday, 10/13, and roadway access will be back in service before 5AM on Monday 10/16.

Access from route 3 to Burgin Parkway will be detoured and police details will be deployed to manage the traffic. MassDOT has been working with the Quincy Police Department in preparation for this construction.

Weekend Detour - The Bottom Line

Route 3 Consturction Map

  • September 22-25
    • Rte. 3 Northbound reduced from 3 lanes to 2 lanes in the work zone.
    • Ramp C closed 
    • Ramp F closed to local traffic
    • Detour via Washington Street
  • October 13-16
    • Rte. 3 Southbound reduced from 3 lanes to 2 lanes in the work zone.
    • Ramp C closed.
    • Ramp F closed to local traffic
    • Detour via Washington Street.